• Mission
    SANIRE promotes advancement of the discipline of rock engineering through the following objectives: Mission
  • Mission (a)
    Encouraging interest and the advancement of education in rock engineering; Mission (a)
  • Mission (b)
    Maintaining professional practice and high standard of ethics; Mission (b)
  • Mission (c)
    Encouraging networking, collaboration and information exchange; Mission (c)
  • Mission (d)
    Identifying, promoting and facilitating rock engineering related research; Mission (d)
  • Mission (e)
    Providing access to the global rock engineering fraternity through the ISRM. Mission (e)
  • Vision
    To promote the interests of a vibrant Southern African rock engineering fraternity Vision

News and updates

RMC Paper 1 Download - Important Information

Friday, 30 March 2012

 Dear SANIRE Member, we are apologizing for any problems being experienced during the download process, but we are experiencing very large download volumes. Be patient and try again. When successful downloading please check the following:

Install Paper 1 Material

o   Download the Installer file from the website
o   Double click of the Installer and allow it to install the information on your computer
o   When done, the Installer will create an Icon on your desktop that reads 'Rock Mechanics Theory', use this icon to open the document. You do not need to open any other files, but work through th...

_____________________________________________________

MOSHing towards zero harm

Monday, 19 March 2012

moshRock related safety is a major issue. The Chamber of Mines' Mine Occupational Safety and Health (MOSH) initiative is helping to address it. Find out more by reading on.

In 2003, representatives of the South African Mining industry - employers, labour unions and government - set historic and significant milestones for health and safety, to be reached by 2013, en route to zero harm for all employees.

The Chamber of Mines realised that the milestones, let alone the targets, would not easily be met without significant effort on the part of mines. Therefore the Chamber of Mines Learning Hub was ...

_____________________________________________________

From maths and computers to rock engineering

Monday, 19 March 2012

rogerjohnsonRoger Johnson's enjoyment of his job is based on the people he works with; the diversity in terms of commodity, geographic location and mining method; and the challenges and opportunities to introduce new technology, better practice and improved solutions. Here, he shares some of his ideas and experiences with Rock Talk.

Roger Johnson (56) had more of an interest in sport, the outdoors, music and social activities than in academics in his time as a scholar as La Salle College on the West Rand, but that was no predictor of his future.

Today, he has a slew of degrees and other qualifications t...

_____________________________________________________

March will bring your first free downloadable paper

Monday, 19 March 2012

exampaperComprehensive rock engineering learning material for the South African mining industry is almost complete – and you can download it for free. Read more about it.

The writing of comprehensive rock engineering material for the South African mining industry started in the first half of 2011. It should be completed by end of March this year. At the time of writing this article, Paper 1 was complete. It should be available for download, free of charge, on the Sanire website by the time you read this article. The other papers will be available for download as and when they are completed.

Why is t...

_____________________________________________________

Design of Merensky Reef crush pillars

Monday, 19 March 2012

saimmlogo2The Bushveld platinum group metal deposits are two distinct, shallow-dipping stratiform tabular ore bodies which strike for many hundreds of kilometres. Mining is extensive, with depths ranging from close-to-surface to 2300 m. The mining method is a variation of planar open stoping. Pillars are widely employed to support the open stopes. In the deeper levels, in-stope pillars are required to fail in a stable manner soon after being cut, and the residual pillar strength is used to stabilize the hangingwall. These pillars are commonly known as crush pillars. Little work has been done in the p...

_____________________________________________________

How Tuks makes positive change a constant

Monday, 19 March 2012

janniemaritzThe University of Pretoria's Jannie Maritz asks: Are teaching and learning really making an impact? At Tuks, he thinks they are. Read on to find out why.

The University of Pretoria's department of Mining Engineering celebrated its 50th anniversary in 2011. The first mining engineering student enrolled for the degree in 1961 and subsequently graduated in 1964.

A lot has changed on and around the campus, yet one thing has stayed the same: The quality of mining engineer graduating has improved. Every year, Tuks Mining is delivering around 30 newly developed mining engineers into the industry. ...

Mar 23 2011

gasstorageMany SANIRE members who have done GDE courses at WITS will be familiar with this case study.  The project was the construction of an LPG storage cavern, consisting of four 14m span galleries, at a depth of about 150m, beneath the Botany Bay harbour, Sydney, Australia.

The owner had budgeted to spend US$100 million on the project, but the cost ended up at about $200 million.  The owner did not believe that the extra cost was his problem, so he sued the designers of the project.

Prof. Dick Stacey from the University of the Witwatersrand was involved in this project as an expert witness on behalf of the owner.  He tells us more…

2.1

2.2

 

 

 

 

 

 

 

 

 

 

 

The manifestation of the problem was a few rock falls, as shown in these pictures, the first about 160 tons. As a result of the falls, the government works inspector stopped the work until he could be satisfied that the support would prevent further falls. This resulted in delays, cost increases, claims, etc. A re-design of rock support was carried out, and the new design involved about four times as much steel as the original design. This clearly indicates a problem with the original design.

In preparing for the arbitration of the dispute, the background and design information was examined in detail. In the Sydney area there are many exposures of the sandstone typical of the rock in which the cavern was excavated.

2.3A good site investigation carried out under the control of the designers.  One of the statements in the investigation report was, “Crossbed surfaces in the sheet sandstone facies represent planes of weakness, indicated by the relatively large number of drill induced core fractures in this facies. Should a cavern roof be placed within the sheet facies, these planes of weakness pose potential problems for roof stability”

There is abundant expert local knowledge of construction in the sandstone rock, and the design was reviewed for third parties (eg, the local Council and residents, who might be concerned about the possibility of a gas leak, etc) by some of these engineers/geologists.  The following are several statements from these reviews:

“… significant zones could exist around the caverns where … the strength criteria … for the rock mass are exceeded”

“… stress induced spalling [expected] to occur 50% to 60% of the time”

“…a significant risk of rock wedges in the range of 18T to 200T” occurring “in the crown and shoulders of the cavern”

“… the geological model appears to be too simplistic and probably incorrect, particularly in terms of the geological structures”

Variability of conditions was not taken into account – geology, geological structure, rock strength, in situ stress, etc were all variable.  A simple example: the UCS of the rock varied between about 25 and 70 MPa, but the calculations were carried out for an average strength of about 40 MPa.  If variability had been considered, the probability of failure indicated would probably have been unacceptably high.2.4

It could have been expected that the review comments would have been addressed by the designers. These review comments proved to be exactly right - popping of rock from surfaces was common; the major rock fall was 160 tons (close to the 200T predicted); prior to the occurrence of the major rock falls, several other falls and rock instability had been observed – equipment was damaged and there was a near miss as far as worker safety was concerned.  These occurrences should have served as a warning that behaviour was not commensurate with design.

At the time the design was being carried out, the Sydney Opera House underground car park was under construction. The design of the support for this excavation had been published, the designers were available to give advice, and the site could be visited for inspection. The support design shown right involves about four times as much steel as the original cavern support design. Therefore, direct transfer of this knowledge might have resulted in a suitable rock support design for the cavern!

The dispute was settled by mediation halfway through the arbitration process.  The mediation process is confidential so I do not know the amount of the settlement.  However, I do know that the owner was happy with it!  I understand that the storage facility is working well and the galleries are unlikely ever to be seen again!

This is what they looked like after excavation.

2.5

What is the message?  The project revealed severe shortcomings with regard to the design process and it cost the designers a lot of money!  A thorough design process is essential:

  • Interpret the geotechnical data thoroughly.
  • Make use of available information and knowledge.
  • Identify the likely mechanisms of behaviour and hence applicable design criteria.
  • Carry out appropriate design calculations and determine likely factors of safety and probabilities of failure.  Remember that numerical analyses are not design calculations, only the tools to use in design.  It is the decisions that are made based on the analysis results that represent the design.
  • Allow for independent reviews of the design.
  • Monitor during excavation to ensure that behaviour (deformations, instability, etc) matches the design, ie that the design is proven.  If not, then changes must be made to the design to correct the situation.

The stress and structure induced instability that occurred in the project were clear indicators that the design was inadequate.

Remember that if you encounter instability, it represents a failure of your design.

Upcoming Events

Mon May 28
EUROCK 2012 - ISRM International Symposium
__________________________
Sun Jun 24
46th US Rock Mechanics / Geomechanics Symposium
__________________________
Tue Aug 07
ISRM Regional Symposium - II South American Symposium on Rock Excavations
__________________________
Mon Oct 15
ARMS 2012 - 7th Asian Rock Mechanics Symposium
__________________________
Thu Oct 25
2012 SANIRE Symposium - “Mechanica Saxorum”
__________________________

Latest Discussions

    • emo
    • Exam Venues
    • Anyone who wrote exams in the Roodepoort venue for May 2012 would know that the venue was noisy thro
    • 2 days, 5 hours ago
    • emo
    • SCO May Exam
    • Does anyone have Mock Exam papers for the May 2012 exam obtained from the relevant courses attended?
    • 6 days, 22 hours ago

ISRM communication

How do you recommend the ISRM increase member communication in South Africa

How should ISRM improve benefits?

What do you think the ISRM should do to improve membership benefits

Benefits of ISRM through SANIRE

What benefits do you as a member see in ISRM membership through SANIRE

ISRMlogo3
SANIRE is a member of the

Get news updates

Subscribe to the RockTalk Newsletter for updates, announcements and a lot more.



Joomla : SANIRE - South Afric

Commodity Charts

Gold charts on InfoMine.com Iron Ore CVRD charts on InfoMine.com Platinum charts on InfoMine.com

We have 26 guests and no members online